Save Our Sausalito

1 Harbor Drive · Current Status · Updated July 7, 2026

City finds the 1 Harbor Drive application incomplete

Rendering of proposed development

The City notified the 1 Harbor Drive applicant that the project application submitted on June 4 is incomplete. A 5-page Notice of Incomplete Application letter was sent to the applicant on June 30. Among many things were discovered by the staff included:

  • Inconsistent height declarations (claiming 64 feet in narrative when plans says 80 feet)
  • Missing reports
  • Outstanding fees

The applicant is required to address all staff comments prior to resubmitting documents for review.